Spectrum@metro (Phase-3)

UPRERAPRJ6037

Uttar PradeshCompleted

Delivered — but late

This project was completed about 24 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 12 Aug 2017Due 7 Dec 2023

Completed.

  1. Registered with RERA

    12 Aug 2017
  2. Original promised completion

    10 Dec 2021

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    7 Dec 2023

    Pushed back ~24 months across 3 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

12 Aug 2017

When the project was registered with RERA.

10 Dec 2021

The deadline committed to at registration.

7 Dec 2023

After all approved extensions.

Handover date, when available.

24 mo delay23.9 mo

How late the finished project was.

3

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
10 Dec 20219 Jun 202209-06-2022 (Six months extension in view of force majeure caused by covid-19 pandemic)
9 Jun 20228 Jun 2023
8 Jun 20237 Dec 2023

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 6 projects — 5 delivered, 1 still active. 6 of 6 (100%) ran late by an average of 17 months.

6 projects6 delayed (100%)0% on time

See BLUE SQUARE INFRASTRUCTURE LLP's full track record →

Official records

View this project on the UP RERA portal

Builder: BLUE SQUARE INFRASTRUCTURE LLP (NAME:BLUE SQUARE INFRASTRUCTURE LLP)