PARSVNATH PRIVILEGE PHASE-1
UPRERAPRJ6060
Delivered — but late
This project was completed about 12 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
30 Jul 2017Original promised completion
31 Jan 2019The deadline the builder committed to at registration.
Revised deadline after extensions
30 Jan 2020Pushed back ~12 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
30 Jul 2017
When the project was registered with RERA.
31 Jan 2019
The deadline committed to at registration.
30 Jan 2020
After all approved extensions.
—
Handover date, when available.
12 mo delay12 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Jan 2019 | 30 Jan 2020 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 6 projects — 6 delivered, 0 still active. 5 of 6 (83%) ran late by an average of 11 months.