Rise Sports Villas , Super 30 Villas

RERA project status · delays · complaints

UPRERAPRJ621633

Gautam Buddha Nagar, Uttar PradeshNewOverdue

Behind schedule

This project is about 30 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 20 Jan 2020Due 29 Dec 2023

Past deadline by ~31 months.

  1. Registered with RERA

    20 Jan 2020
  2. Original promised completion

    30 Jun 2023

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    29 Dec 2023

    Pushed back ~6 months across 1 extension.

  4. Today — still not completed

    About 31 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

20 Jan 2020

When the project was registered with RERA.

30 Jun 2023

The deadline committed to at registration.

29 Dec 2023

After all approved extensions.

Handover date, when available.

30 mo overdue29.8 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On UP RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Jun 202329 Dec 202329-12-2023 (Six months extension in view of force majeure caused by covid-19 pandemic)

Official records

View this project on the UP RERA portal

Data last refreshed 20 Jun 2026.