Gaur Saundaryam (Phase-2)
UPRERAPRJ6335
Behind schedule
This project is about 57 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~57 months.
Registered with RERA
31 Jul 2017Original promised completion
31 Mar 2021The deadline the builder committed to at registration.
Revised deadline after extensions
29 Sept 2021Pushed back ~6 months across 1 extension.
Today — still not completed
About 57 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
31 Jul 2017
When the project was registered with RERA.
31 Mar 2021
The deadline committed to at registration.
29 Sept 2021
After all approved extensions.
—
Handover date, when available.
57 mo overdue56.8 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Mar 2021 | 29 Sept 2021 | 29-09-2021 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.
Official records
Builder: GAURSONS REALTY PRIVATE LIMITED (UPRERAPRM1867)
Data last refreshed 20 Jun 2026.