RUDRA AQUACASA

RERA project status · delays · complaints

UPRERAPRJ6649

Gautam Buddha Nagar, Uttar PradeshOngoingOverdue

Behind schedule

This project is about 6 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 3 Aug 2017Due 31 Dec 2025

Past deadline by ~7 months.

  1. Registered with RERA

    3 Aug 2017
  2. Original promised completion

    31 Dec 2020

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    31 Dec 2025

    Pushed back ~60 months across 3 extensions.

  4. Today — still not completed

    About 7 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

3 Aug 2017

When the project was registered with RERA.

31 Dec 2020

The deadline committed to at registration.

31 Dec 2025

After all approved extensions.

Handover date, when available.

6 mo overdue5.7 mo

How far past deadline an ongoing project is.

3

More extensions can signal execution risk.

On UP RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
29 Mar 202331 Dec 2025
31 Dec 202030 Jun 202130-06-2021 (Six months extension in view of force majeure caused by covid-19 pandemic)
30 Jun 202129 Mar 2023