Global Business Square

RERA project status · delays · complaints

UPRERAPRJ6745

Uttar PradeshCompleted

Delivered — but late

This project was completed about 27 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 5 Aug 2017Due 26 Sept 2024

Completed.

  1. Registered with RERA

    5 Aug 2017
  2. Original promised completion

    28 Jun 2022

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    26 Sept 2024

    Pushed back ~27 months across 2 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

5 Aug 2017

When the project was registered with RERA.

28 Jun 2022

The deadline committed to at registration.

26 Sept 2024

After all approved extensions.

—

Handover date, when available.

27 mo delay27 mo

How late the finished project was.

2

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
28 Jun 202227 Dec 202227-12-2022 (Six months extension in view of force majeure caused by covid-19 pandemic)
27 Dec 202226 Sept 2024—

Official records

View this project on the UP RERA portal

Data last refreshed 21 Jun 2026.