Golden I Phase-I

RERA project status · delays · complaints

UPRERAPRJ6747

Uttar PradeshCompleted

Delivered — but late

This project was completed about 18 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 9 Aug 2017Due 13 Dec 2023

Completed.

  1. Registered with RERA

    9 Aug 2017
  2. Original promised completion

    15 Jun 2022

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    13 Dec 2023

    Pushed back ~18 months across 2 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

9 Aug 2017

When the project was registered with RERA.

15 Jun 2022

The deadline committed to at registration.

13 Dec 2023

After all approved extensions.

—

Handover date, when available.

18 mo delay17.9 mo

How late the finished project was.

2

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
15 Jun 202214 Dec 202214-12-2022 (Six months extension in view of force majeure caused by covid-19 pandemic)
14 Dec 202213 Dec 2023—