Golden I Phase-I
UPRERAPRJ6747
Delivered — but late
This project was completed about 18 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
9 Aug 2017Original promised completion
15 Jun 2022The deadline the builder committed to at registration.
Revised deadline after extensions
13 Dec 2023Pushed back ~18 months across 2 extensions.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
9 Aug 2017
When the project was registered with RERA.
15 Jun 2022
The deadline committed to at registration.
13 Dec 2023
After all approved extensions.
—
Handover date, when available.
18 mo delay17.9 mo
How late the finished project was.
2
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 15 Jun 2022 | 14 Dec 2022 | 14-12-2022 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 14 Dec 2022 | 13 Dec 2023 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 3 projects — 2 delivered, 1 still active. 2 of 3 (67%) ran late by an average of 21 months.
See OCEAN INFRAHEIGHTS PRIVATE LIMITED's full track record →
Official records
Builder: OCEAN INFRAHEIGHTS PRIVATE LIMITED (NAME:OCEAN INFRAHEIGHTS PRIVATE LIMITED)
Data last refreshed 21 Jun 2026.