TOWN CENTRAL - PHASE-I
UPRERAPRJ7066
Delivered — but late
This project was completed about 18 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
31 Jul 2017Original promised completion
15 Aug 2022The deadline the builder committed to at registration.
Revised deadline after extensions
14 Feb 2024Pushed back ~18 months across 2 extensions.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
31 Jul 2017
When the project was registered with RERA.
15 Aug 2022
The deadline committed to at registration.
14 Feb 2024
After all approved extensions.
—
Handover date, when available.
18 mo delay18 mo
How late the finished project was.
2
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 15 Aug 2022 | 14 Feb 2023 | 14-02-2023 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 14 Feb 2023 | 14 Feb 2024 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 3 projects — 1 delivered, 2 still active. 2 of 3 (67%) ran late by an average of 18 months.
Official records
Builder: PKS BUILDMART PRIVATE LIMITED (NAME:PKS BUILDMART PRIVATE LIMITED)
Data last refreshed 21 Jun 2026.