F PREMIERE (PHASE 3)
RERA project status · delays · complaints
UPRERAPRJ7195
Behind schedule
This project is past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~1 month.
Registered with RERA
1 Aug 2017Original promised completion
30 Mar 2022The deadline the builder committed to at registration.
Revised deadline after extensions
9 Jul 2026Pushed back ~51 months across 4 extensions.
Today — still not completed
About 1 month past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
1 Aug 2017
When the project was registered with RERA.
30 Mar 2022
The deadline committed to at registration.
9 Jul 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
4
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Mar 2022 | 29 Sept 2022 | 29-09-2022 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 29 Sept 2022 | 28 Jun 2024 | — |
| 28 Jun 2024 | 10 Jul 2025 | — |
| 10 Jul 2025 | 9 Jul 2026 | — |