BOULEVARD WALK (PHASE 1)
UPRERAPRJ7271
Behind schedule
This project is about 8 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~8 months.
Registered with RERA
4 Aug 2017Original promised completion
31 Mar 2020The deadline the builder committed to at registration.
Revised deadline after extensions
31 Oct 2025Pushed back ~67 months across 3 extensions.
Today — still not completed
About 8 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
4 Aug 2017
When the project was registered with RERA.
31 Mar 2020
The deadline committed to at registration.
31 Oct 2025
After all approved extensions.
—
Handover date, when available.
8 mo overdue7.7 mo
How far past deadline an ongoing project is.
3
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Mar 2020 | 30 Sept 2020 | 30-09-2020 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 30 Sept 2020 | 29 Jun 2022 | — |
| 29 Jun 2022 | 31 Oct 2025 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 0 delivered, 4 still active. 4 of 4 (100%) ran late.
See REGAL EMPORIA INFRATECH PRIVATE LIMITED's full track record →
Official records
Builder: REGAL EMPORIA INFRATECH PRIVATE LIMITED (NAME:REGAL EMPORIA INFRATECH PRIVATE LIMITED)
Data last refreshed 20 Jun 2026.