SUNTWILIGHT - RECREATIONAL - PHASE - I
UPRERAPRJ7280
Behind schedule
This project is about 28 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~28 months.
Registered with RERA
2 Aug 2017Original promised completion
15 Aug 2022The deadline the builder committed to at registration.
Revised deadline after extensions
13 Feb 2024Pushed back ~18 months across 2 extensions.
Today — still not completed
About 28 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
2 Aug 2017
When the project was registered with RERA.
15 Aug 2022
The deadline committed to at registration.
13 Feb 2024
After all approved extensions.
—
Handover date, when available.
28 mo overdue28.3 mo
How far past deadline an ongoing project is.
2
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 15 Aug 2022 | 14 Feb 2023 | 14-02-2023 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 14 Feb 2023 | 13 Feb 2024 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 3 projects — 0 delivered, 3 still active. 3 of 3 (100%) ran late.
See SUNRISE STRUCTURES & DEVELOPERS PRIVATE LIMITED's full track record →
Official records
Builder: SUNRISE STRUCTURES & DEVELOPERS PRIVATE LIMITED (NAME:SUNRISE STRUCTURES & DEVELOPERS PRIVATE LIMITED)
Data last refreshed 20 Jun 2026.