TOWN CENTRAL - PHASE-II
UPRERAPRJ7355
Behind schedule
This project is about 7 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~7 months.
Registered with RERA
1 Aug 2017Original promised completion
15 Aug 2023The deadline the builder committed to at registration.
Revised deadline after extensions
11 Nov 2025Pushed back ~27 months across 3 extensions.
Today — still not completed
About 7 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
1 Aug 2017
When the project was registered with RERA.
15 Aug 2023
The deadline committed to at registration.
11 Nov 2025
After all approved extensions.
—
Handover date, when available.
7 mo overdue7.3 mo
How far past deadline an ongoing project is.
3
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 15 Aug 2023 | 14 Feb 2024 | 14-02-2024 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 14 Feb 2024 | 14 Feb 2025 | — |
| 14 Feb 2025 | 11 Nov 2025 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 3 projects — 1 delivered, 2 still active. 2 of 3 (67%) ran late by an average of 18 months.
Official records
Builder: PKS BUILDMART PRIVATE LIMITED (NAME:PKS BUILDMART PRIVATE LIMITED)
Data last refreshed 20 Jun 2026.