The journey from RERA registration to completion, in order.

Registered 14 Aug 2017Due 31 Jul 2026

Past deadline by ~0 months.

  1. Registered with RERA

    14 Aug 2017
  2. Original promised completion

    31 Dec 2018

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    31 Jul 2026

    Pushed back ~91 months across 6 extensions.

  4. Today — still not completed

    About 0 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

14 Aug 2017

When the project was registered with RERA.

31 Dec 2018

The deadline committed to at registration.

31 Jul 2026

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

6

More extensions can signal execution risk.

On UP RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Dec 201831 Dec 2019
31 Dec 201930 May 2020
30 May 202029 Nov 202029-11-2020 (Six months extension in view of force majeure caused by covid-19 pandemic)
29 Nov 202031 Mar 2021
31 Mar 202131 Jul 2025
31 Jul 202531 Jul 2026