Future Estate(Phase-Fe-2)
UPRERAPRJ7369
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
14 Aug 2017Original promised completion
30 Jun 2019The deadline the builder committed to at registration.
Revised deadline after extensions
31 Jul 2026Pushed back ~85 months across 4 extensions.
Today — in progress
About 1 month left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
14 Aug 2017
When the project was registered with RERA.
30 Jun 2019
The deadline committed to at registration.
31 Jul 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
4
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2019 | 9 Jun 2020 | — |
| 9 Jun 2020 | 8 Dec 2020 | 08-12-2020 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 8 Dec 2020 | 30 Sept 2021 | — |
| 30 Sept 2021 | 31 Jul 2026 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 7 projects — 2 delivered, 5 still active. 2 of 7 (29%) ran late by an average of 76 months.
Official records
Builder: FUTUREWORLD GREENHOMES PVT. LTD. (NAME:FUTUREWORLD GREENHOMES PVT. LTD.)
Data last refreshed 20 Jun 2026.