Godrej Palm Retreat 1
UPRERAPRJ745601
Delivered — but late
This project was completed about 6 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
11 Jun 2019Original promised completion
4 Dec 2024The deadline the builder committed to at registration.
Revised deadline after extensions
3 Jun 2025Pushed back ~6 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
11 Jun 2019
When the project was registered with RERA.
4 Dec 2024
The deadline committed to at registration.
3 Jun 2025
After all approved extensions.
—
Handover date, when available.
6 mo delay6 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 4 Dec 2024 | 3 Jun 2025 | 03-06-2025 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Weak track record
Tracking 3 projects — 2 delivered, 1 still active. 2 of 3 (67%) ran late by an average of 3 months.
See ACE INFRACITY DEVELOPERS PRIVATE LIMITED's full track record →
Official records
Builder: ACE INFRACITY DEVELOPERS PRIVATE LIMITED (NAME:ACE INFRACITY DEVELOPERS PRIVATE LIMITED)
Data last refreshed 21 Jun 2026.