Morpheus Pratiksha

RERA project status · delays · complaints

UPRERAPRJ7881

Uttar PradeshCompleted

Delivered — but late

This project was completed about 121 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 3 Aug 2017Due 6 Feb 2030

Completed.

  1. Registered with RERA

    3 Aug 2017
  2. Original promised completion

    31 Dec 2019

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    6 Feb 2030

    Pushed back ~121 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

3 Aug 2017

When the project was registered with RERA.

31 Dec 2019

The deadline committed to at registration.

6 Feb 2030

After all approved extensions.

Handover date, when available.

121 mo delay121.2 mo

How late the finished project was.

1

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Dec 20196 Feb 2030

Official records

View this project on the UP RERA portal

Data last refreshed 21 Jun 2026.