County One O Seven
RERA project status · delays · complaints
UPRERAPRJ837374
Delivered — but late
This project was completed about 6 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
18 Mar 2019Original promised completion
25 Dec 2023The deadline the builder committed to at registration.
Revised deadline after extensions
24 Jun 2024Pushed back ~6 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
18 Mar 2019
When the project was registered with RERA.
25 Dec 2023
The deadline committed to at registration.
24 Jun 2024
After all approved extensions.
—
Handover date, when available.
6 mo delay6 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 25 Dec 2023 | 24 Jun 2024 | 24-06-2024 (Six months extension in view of force majeure caused by covid-19 pandemic) |
Official records
Data last refreshed 21 Jun 2026.