PANCHSHEEL GREENS - II (TOWER - D1,D2& E5)

RERA project status · delays · complaints

UPRERAPRJ8592

Uttar PradeshCompleted

Delivered — but late

This project was completed about 63 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 12 Aug 2017Due 30 Nov 2026

Completed.

  1. Registered with RERA

    12 Aug 2017
  2. Original promised completion

    31 Aug 2021

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    30 Nov 2026

    Pushed back ~63 months across 3 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

12 Aug 2017

When the project was registered with RERA.

31 Aug 2021

The deadline committed to at registration.

30 Nov 2026

After all approved extensions.

Handover date, when available.

63 mo delay63 mo

How late the finished project was.

3

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Aug 202128 Feb 202228-02-2022 (Six months extension in view of force majeure caused by covid-19 pandemic)
28 Feb 202227 Nov 2023
27 Nov 202330 Nov 2026