PANCHSHEEL GREENS - II (TOWER - E6,E7,D3 &D4)
UPRERAPRJ8595
Delivered — but late
This project was completed about 48 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
12 Aug 2017Original promised completion
30 Nov 2022The deadline the builder committed to at registration.
Revised deadline after extensions
30 Nov 2026Pushed back ~48 months across 3 extensions.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
12 Aug 2017
When the project was registered with RERA.
30 Nov 2022
The deadline committed to at registration.
30 Nov 2026
After all approved extensions.
—
Handover date, when available.
48 mo delay48 mo
How late the finished project was.
3
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Nov 2022 | 29 May 2023 | 29-05-2023 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 29 May 2023 | 28 Feb 2025 | — |
| 28 Feb 2025 | 30 Nov 2026 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 12 projects — 11 delivered, 1 still active. 8 of 12 (67%) ran late by an average of 17 months.
Official records
Builder: PANCHSHEEL BUILDTECH PVT. LTD. (NAME:PANCHSHEEL BUILDTECH PVT. LTD.)
Data last refreshed 21 Jun 2026.