PANCHSHEEL GREENS PHASE - 1 (B1 TO B3,F4 TO F6 & C
UPRERAPRJ8832
Delivered on time
Marked completed on the registry on or before the promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
11 Aug 2017Original promised completion
30 May 2018The deadline the builder committed to at registration.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
11 Aug 2017
When the project was registered with RERA.
30 May 2018
The deadline committed to at registration.
30 May 2018
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 12 projects — 11 delivered, 1 still active. 8 of 12 (67%) ran late by an average of 17 months.
Official records
Builder: PANCHSHEEL BUILDTECH PVT. LTD. (NAME:PANCHSHEEL BUILDTECH PVT. LTD.)
Data last refreshed 21 Jun 2026.