PANCHSHEEL PINNACLE PHASE - 1 (TOWER - F2 & F3) PA

RERA project status · delays · complaints

UPRERAPRJ8845

Uttar PradeshCompleted

Delivered — but late

This project was completed about 13 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 11 Aug 2017Due 29 Sept 2020

Completed.

  1. Registered with RERA

    11 Aug 2017
  2. Original promised completion

    31 Aug 2019

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    29 Sept 2020

    Pushed back ~13 months across 2 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

11 Aug 2017

When the project was registered with RERA.

31 Aug 2019

The deadline committed to at registration.

29 Sept 2020

After all approved extensions.

Handover date, when available.

13 mo delay13 mo

How late the finished project was.

2

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Aug 201931 Mar 2020
31 Mar 202029 Sept 202029-09-2020 (Six months extension in view of force majeure caused by covid-19 pandemic)