PANCHSHEEL PINNACLE PHASE-2 (TOWER F1)PART OF PANC
UPRERAPRJ8855
Delivered — but late
This project was completed about 27 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
11 Aug 2017Original promised completion
30 Nov 2020The deadline the builder committed to at registration.
Revised deadline after extensions
28 Feb 2023Pushed back ~27 months across 3 extensions.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
11 Aug 2017
When the project was registered with RERA.
30 Nov 2020
The deadline committed to at registration.
28 Feb 2023
After all approved extensions.
—
Handover date, when available.
27 mo delay27 mo
How late the finished project was.
3
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Nov 2020 | 29 May 2021 | 29-05-2021 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 29 May 2021 | 29 May 2022 | — |
| 29 May 2022 | 28 Feb 2023 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 12 projects — 11 delivered, 1 still active. 8 of 12 (67%) ran late by an average of 17 months.