← Back to search

HIMALAYA PRIDE (PHASE 3 : TOWER D)

UPRERAPRJ8898

Uttar PradeshCompleted

Delivered — but late

This project was completed about 6 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 9 Aug 2017Due 30 Jun 2021

Completed.

  1. Registered with RERA

    9 Aug 2017
  2. Original promised completion

    31 Dec 2020

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    30 Jun 2021

    Pushed back ~6 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

9 Aug 2017

When the project was registered with RERA.

31 Dec 2020

The deadline committed to at registration.

30 Jun 2021

After all approved extensions.

Handover date, when available.

6 mo delay6 mo

How late the finished project was.

1

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Dec 202030 Jun 202130-06-2021 (Six months extension in view of force majeure caused by covid-19 pandemic)

About the builder

How this developer has performed across all their tracked projects.

Mixed track record

Tracking 3 projects — 3 delivered, 0 still active. 1 of 3 (33%) ran late by an average of 2 months.

3 projects1 delayed (33%)67% on time

See HIMALAYA REALESTATE PVT LTD's full track record →

Official records

View this project on the UP RERA portal

Builder: HIMALAYA REALESTATE PVT LTD (NAME:HIMALAYA REALESTATE PVT LTD)

Data last refreshed 21 Jun 2026.