Gautam Buddha Nagar, Uttar PradeshOngoingOverdue

Behind schedule

This project is about 19 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 15 Aug 2017Due 23 Nov 2024

Past deadline by ~19 months.

  1. Registered with RERA

    15 Aug 2017
  2. Original promised completion

    7 Jul 2021

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    23 Nov 2024

    Pushed back ~41 months across 4 extensions.

  4. Today — still not completed

    About 19 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

15 Aug 2017

When the project was registered with RERA.

7 Jul 2021

The deadline committed to at registration.

23 Nov 2024

After all approved extensions.

Handover date, when available.

19 mo overdue19 mo

How far past deadline an ongoing project is.

4

More extensions can signal execution risk.

On UP RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
7 Jul 20216 Jan 202206-01-2022 (Six months extension in view of force majeure caused by covid-19 pandemic)
6 Jan 20225 Sept 2023
5 Sept 202323 May 2024
23 May 202423 Nov 2024

About the builder

How this developer has performed across all their tracked projects.

Mixed track record

Tracking 3 projects — 1 delivered, 2 still active. 2 of 3 (67%) ran late.

3 projects2 delayed (67%)100% on time

See SKV INFOTECH PRIVATE LIMITED's full track record →

Official records

View this project on the UP RERA portal

Builder: SKV INFOTECH PRIVATE LIMITED (NAME:SKV INFOTECH PRIVATE LIMITED)

Data last refreshed 20 Jun 2026.