GRANDTHUM PHASE V
RERA project status · delays · complaints
UPRERAPRJ957104
Behind schedule
This project is past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~1 month.
Registered with RERA
2 Sept 2019Original promised completion
30 Jun 2023The deadline the builder committed to at registration.
Revised deadline after extensions
26 Sept 2026Pushed back ~39 months across 4 extensions.
Today — still not completed
About 1 month past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
2 Sept 2019
When the project was registered with RERA.
30 Jun 2023
The deadline committed to at registration.
26 Sept 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
4
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2023 | 29 Dec 2023 | 29-12-2023 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 29 Dec 2023 | 28 Dec 2024 | — |
| 28 Dec 2024 | 27 Sept 2025 | — |
| 27 Sept 2025 | 26 Sept 2026 | — |
Official records
Data last refreshed 20 Jun 2026.