GRANDTHUM PHASE V
UPRERAPRJ957104
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
2 Sept 2019Original promised completion
30 Jun 2023The deadline the builder committed to at registration.
Revised deadline after extensions
26 Sept 2026Pushed back ~39 months across 4 extensions.
Today — in progress
About 3 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
2 Sept 2019
When the project was registered with RERA.
30 Jun 2023
The deadline committed to at registration.
26 Sept 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
4
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2023 | 29 Dec 2023 | 29-12-2023 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 29 Dec 2023 | 28 Dec 2024 | — |
| 28 Dec 2024 | 27 Sept 2025 | — |
| 27 Sept 2025 | 26 Sept 2026 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 3 delivered, 1 still active. 3 of 4 (75%) ran late by an average of 39 months.
Official records
Builder: A L SOFTWEB PRIVATE LIMITED (NAME:A L SOFTWEB PRIVATE LIMITED)
Data last refreshed 20 Jun 2026.