Gautam Buddha Nagar, Uttar PradeshOngoingOverdue

Behind schedule

This project is about 102 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 12 Aug 2017Due 31 Dec 2017

Past deadline by ~102 months.

  1. Registered with RERA

    12 Aug 2017
  2. Original promised completion

    31 Dec 2017

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 102 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

12 Aug 2017

When the project was registered with RERA.

31 Dec 2017

The deadline committed to at registration.

31 Dec 2017

After all approved extensions.

Handover date, when available.

102 mo overdue101.7 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On UP RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.

1 projects1 delayed (100%)

See M/S OMKAR NESTS PVT. LTD.'s full track record →

Official records

View this project on the UP RERA portal

Builder: M/S OMKAR NESTS PVT. LTD. (NAME:M/S OMKAR NESTS PVT. LTD.)

Data last refreshed 20 Jun 2026.