CENTRADE BUSINESS PARK PHASE I

RERA project status · delays · complaints

UPRERAPRJ9635

Gautam Buddha Nagar, Uttar PradeshOngoingOverdue

Behind schedule

This project is about 64 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 14 Aug 2017Due 28 Feb 2021

Past deadline by ~65 months.

  1. Registered with RERA

    14 Aug 2017
  2. Original promised completion

    29 Feb 2020

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    28 Feb 2021

    Pushed back ~12 months across 1 extension.

  4. Today — still not completed

    About 65 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

14 Aug 2017

When the project was registered with RERA.

29 Feb 2020

The deadline committed to at registration.

28 Feb 2021

After all approved extensions.

Handover date, when available.

64 mo overdue63.8 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On UP RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
29 Feb 202028 Feb 2021

Official records

View this project on the UP RERA portal

Data last refreshed 20 Jun 2026.