ACE INFRACITY DEVELOPERS PRIVATE LIMITED

NAME:ACE INFRACITY DEVELOPERS PRIVATE LIMITED

Weak track record

Tracking 3 projects — 2 delivered, 1 still active. 2 of 3 (67%) ran late by an average of 3 months.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

1 Delivered on time1 Delivered late1 Overdue

Key numbers

Total projects

3

Active

1

Completed

2

Delayed

2 (67%)

Late or overdue

Avg delay

3 mo

Worst: 6 mo

On-time rate

50%

Of completed projects

Extension rate

67%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Ace Parkway
UPRERAPRJ4514
Gautam Buddha Nagar
UP
9 Aug 201731 Dec 2021Overdue36 mo overdue
Godrej Palm Retreat 1
UPRERAPRJ745601
UP
11 Jun 20194 Dec 2024Completed6 mo delay
Godrej Palm Retreat 2
UPRERAPRJ124632
UP
11 Jun 201930 Dec 2025CompletedOn track