BLUE SQUARE INFRASTRUCTURE LLP

NAME:BLUE SQUARE INFRASTRUCTURE LLP

Poor track record

Tracking 6 projects — 5 delivered, 1 still active. 6 of 6 (100%) ran late by an average of 17 months.

Delivery breakdown

How this builder's 6 tracked projects are split by outcome.

5 Delivered late1 Overdue

Key numbers

Total projects

6

Active

1

Completed

5

Delayed

6 (100%)

Late or overdue

Avg delay

16.8 mo

Worst: 23.9 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (6)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
SPECTRUM METRO BLOCK- A and E
UPRERAPRJ427696
Gautam Buddha Nagar
UP
11 Jun 201930 Apr 2024Overdue20 mo overdue
Spectrum@metro (Phase-3)
UPRERAPRJ6037
UP
12 Aug 201710 Dec 2021Completed24 mo delay
Spectrum@metro (Phase-4)
UPRERAPRJ6040
UP
12 Aug 201731 Dec 2021Completed24 mo delay
spectrum@Metro ( Phase-1)
UPRERAPRJ6018
UP
12 Aug 201731 Dec 2020Completed6 mo delay
spectrum@metro(Phase-2)
UPRERAPRJ6028
UP
12 Aug 201731 Dec 2020Completed18 mo delay
SPECTRUM METRO
UPRERAPRJ17035
UP
16 Jul 20181 Nov 2023Completed12 mo delay