CCI PROJECTS PRIVATE LIMITED

RERA delivery track record · complaints · project delays

NAME:CCI PROJECTS

Weak track record

Tracking 6 projects — 2 delivered, 4 still active. 2 of 6 (33%) ran late by an average of 12 months.

Delivery breakdown

How this builder's 6 tracked projects are split by outcome.

1 Delivered on time1 Delivered late1 Overdue3 In progress

Key numbers

Total projects

6

Active

4

Completed

2

Delayed

2 (33%)

Late or overdue

Avg delay

12 mo

Worst: 24 mo

On-time rate

50%

Of completed projects

Extension rate

33%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (6)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800002287
Mumbai Suburban · MH
Mumbai Suburban
MH
31 Jul 201731 Dec 2018CompletedOn track
P51800003067
Mumbai Suburban · MH
Mumbai Suburban
MH
4 Aug 201731 Dec 2019Completed24 mo delay
P51800018662
Mumbai Suburban · MH
Mumbai Suburban
MH
22 Nov 201830 Dec 2021Overdue12 mo overdue
P51800050351
Mumbai Suburban · MH
Mumbai Suburban
MH
5 Apr 202331 Aug 2028In progressOn track
P51800053578
Mumbai Suburban · MH
Mumbai Suburban
MH
10 Nov 202331 Oct 2029In progressOn track
P51800055489
Mumbai Suburban · MH
Mumbai Suburban
MH
2 Apr 202430 Jun 2030In progressOn track