CCI PROJECTS PRIVATE LIMITED
RERA delivery track record · complaints · project delays
NAME:CCI PROJECTS
D44/100
Weak track record
Tracking 6 projects — 2 delivered, 4 still active. 2 of 6 (33%) ran late by an average of 12 months.
Delivery breakdown
How this builder's 6 tracked projects are split by outcome.
Key numbers
Total projects
6
Active
4
Completed
2
Delayed
2 (33%)
Late or overdue
Avg delay
12 mo
Worst: 24 mo
On-time rate
50%
Of completed projects
Extension rate
33%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (6)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800002287 Mumbai Suburban · MH | Mumbai Suburban MH | 31 Jul 2017 | 31 Dec 2018 | Completed | On track |
P51800003067 Mumbai Suburban · MH | Mumbai Suburban MH | 4 Aug 2017 | 31 Dec 2019 | Completed | 24 mo delay |
P51800018662 Mumbai Suburban · MH | Mumbai Suburban MH | 22 Nov 2018 | 30 Dec 2021 | Overdue | 12 mo overdue |
P51800050351 Mumbai Suburban · MH | Mumbai Suburban MH | 5 Apr 2023 | 31 Aug 2028 | In progress | On track |
P51800053578 Mumbai Suburban · MH | Mumbai Suburban MH | 10 Nov 2023 | 31 Oct 2029 | In progress | On track |
P51800055489 Mumbai Suburban · MH | Mumbai Suburban MH | 2 Apr 2024 | 30 Jun 2030 | In progress | On track |