Mumbai Suburban, MaharashtraResidential / Group HousingCompleted

Delivered on time

Marked completed on the registry on or before the promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 31 Jul 2017Due 31 Dec 2018

Completed.

  1. Registered with RERA

    31 Jul 2017
  2. Original promised completion

    31 Dec 2018

    The deadline the builder committed to at registration.

  3. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

31 Jul 2017

When the project was registered with RERA.

31 Dec 2018

The deadline committed to at registration.

31 Dec 2018

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

10

Complaints against the builder

0

Often reported per project on MahaRERA

About the builder

How this developer has performed across all their tracked projects.

Weak track record

Tracking 2 projects — 2 delivered, 0 still active. 1 of 2 (50%) ran late by an average of 12 months. Limited history — read the project list before drawing conclusions.

2 projects1 delayed (50%)50% on time

See CCI PROJECTS PRIVATE LIMITED's full track record →

Official records

View this project on the MahaRERA portal

Builder: CCI PROJECTS PRIVATE LIMITED (NAME:CCI PROJECTS PRIVATE LIMITED)

Data last refreshed 21 Jun 2026.