DISHA CONSTRUCTION
NAME:DISHA CONSTRUCTION
F0/100
Poor track record
Tracking 3 projects — 3 delivered, 0 still active. 3 of 3 (100%) ran late by an average of 32 months.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
0
Completed
3
Delayed
3 (100%)
Late or overdue
Avg delay
32 mo
Worst: 48 mo
On-time rate
0%
Of completed projects
Extension rate
100%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| SWASTIK PHASE 1 P51800002197 | Mumbai Suburban MH | 31 Jul 2017 | 31 Dec 2019 | Completed | 48 mo delay |
| DATTA RAMANAND CHS LTD P51800001236 | Mumbai Suburban MH | 27 Jul 2017 | 31 Dec 2019 | Completed | 24 mo delay |
| SAT ANUPA CHS PHASE 1 P51800001640 | Mumbai Suburban MH | 29 Jul 2017 | 31 Mar 2020 | Completed | 24 mo delay |