DISHA CONSTRUCTION

NAME:DISHA CONSTRUCTION

Poor track record

Tracking 3 projects — 3 delivered, 0 still active. 3 of 3 (100%) ran late by an average of 32 months.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

3 Delivered late

Key numbers

Total projects

3

Active

0

Completed

3

Delayed

3 (100%)

Late or overdue

Avg delay

32 mo

Worst: 48 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
SWASTIK PHASE 1
P51800002197
Mumbai Suburban
MH
31 Jul 201731 Dec 2019Completed48 mo delay
DATTA RAMANAND CHS LTD
P51800001236
Mumbai Suburban
MH
27 Jul 201731 Dec 2019Completed24 mo delay
SAT ANUPA CHS PHASE 1
P51800001640
Mumbai Suburban
MH
29 Jul 201731 Mar 2020Completed24 mo delay