TULIP PHASE 1

P51800024339

Mumbai Suburban, MaharashtraResidential / Group HousingCompleted

Delivered on time

Marked completed on the registry on or before the promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 5 Feb 2020Due 30 Jan 2025

Completed.

  1. Registered with RERA

    5 Feb 2020
  2. Original promised completion

    30 Jan 2025

    The deadline the builder committed to at registration.

  3. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

5 Feb 2020

When the project was registered with RERA.

30 Jan 2025

The deadline committed to at registration.

30 Jan 2025

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 4 projects — 4 delivered, 0 still active. 3 of 4 (75%) ran late by an average of 24 months.

4 projects3 delayed (75%)25% on time

See DISHA CONSTRUCTION's full track record →

Official records

View this project on the MahaRERA portal

Builder: DISHA CONSTRUCTION (NAME:DISHA CONSTRUCTION)

Data last refreshed 22 Jun 2026.