HIRANIMANTHAN BUILDERS AND DEVELOPERS
RERA delivery track record · complaints · project delays
NAME:HIRANIMANTHAN BUILDERS AND DEVELOPERS
F9/100
Poor track record
Tracking 6 projects — 4 delivered, 2 still active. 5 of 6 (83%) ran late by an average of 39 months.
Delivery breakdown
How this builder's 6 tracked projects are split by outcome.
Key numbers
Total projects
6
Active
2
Completed
4
Delayed
5 (83%)
Late or overdue
Avg delay
38.5 mo
Worst: 59 mo
On-time rate
25%
Of completed projects
Extension rate
67%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (6)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800004914 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Aug 2017 | 31 Dec 2019 | Completed | 59 mo delay |
P51800003413 Mumbai Suburban · MH | Mumbai Suburban MH | 5 Aug 2017 | 31 Mar 2020 | Completed | 48 mo delay |
P51800003741 Mumbai Suburban · MH | Mumbai Suburban MH | 6 Aug 2017 | 31 Dec 2019 | Completed | 47 mo delay |
P51800008227 Mumbai Suburban · MH | Mumbai Suburban MH | 18 Aug 2017 | 30 Dec 2019 | Overdue | 7 mo overdue |
P51800025091 Mumbai Suburban · MH | Mumbai Suburban MH | 18 Mar 2020 | 30 Mar 2026 | Completed | On track |
P51800031567 Mumbai Suburban · MH | Mumbai Suburban MH | 31 Oct 2021 | 31 Dec 2025 | Overdue | 6 mo overdue |