SWANAND BLDG NO 33
P51800004914
Delivered — but late
This project was completed about 59 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
9 Aug 2017Original promised completion
31 Dec 2019The deadline the builder committed to at registration.
Revised deadline after extensions
30 Nov 2024Pushed back ~59 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
9 Aug 2017
When the project was registered with RERA.
31 Dec 2019
The deadline committed to at registration.
30 Nov 2024
After all approved extensions.
—
Handover date, when available.
59 mo delay59 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Dec 2019 | 30 Nov 2024 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 3 delivered, 1 still active. 4 of 4 (100%) ran late by an average of 51 months.
See HIRANIMANTHAN BUILDERS AND DEVELOPERS's full track record →