Hubtown Limited
NAME:Hubtown Limited
C55/100
Mixed track record
Tracking 14 projects — 9 delivered, 5 still active. 4 of 14 (29%) ran late by an average of 6 months.
Delivery breakdown
How this builder's 14 tracked projects are split by outcome.
Key numbers
Total projects
14
Active
5
Completed
9
Delayed
4 (29%)
Late or overdue
Avg delay
6.2 mo
Worst: 18 mo
On-time rate
56%
Of completed projects
Extension rate
29%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (14)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| Hubtown Greenwoods A wing P51700000365 | Thane MH | 15 Jul 2017 | 31 Jul 2018 | Completed | 2 mo delay |
| Hubtown Greenwoods D Wing P51700000369 | Thane MH | 15 Jul 2017 | 31 Jul 2019 | Completed | 18 mo delay |
| Hubtown Greenwoods F Wing P51700000602 | Thane MH | 18 Jul 2017 | 31 Jul 2019 | Completed | 18 mo delay |
| Hubtown Greenwoods - C Wing P51700012016 | Thane MH | 1 Sept 2017 | 31 Jul 2018 | Completed | On track |
| Hubtown Premiere Residences - Bel Air P51800005688 | Mumbai Suburban MH | 11 Aug 2017 | 31 Jul 2026 | In progress | On track |
| Hubtown Premiere Residences - Tower 2 P51800006839 | Mumbai Suburban MH | 16 Aug 2017 | 31 Jul 2029 | In progress | On track |
| Hubtown Premiere Residences - Tower 3 P51800002977 | Mumbai Suburban MH | 4 Aug 2017 | 31 Jul 2029 | In progress | On track |
| Hubtown Greenwoods E Wing P51700000358 | Thane MH | 15 Jul 2017 | 31 Jul 2019 | Completed | 18 mo delay |
| Hubtown Greenwoods B wing P51700004458 | Thane MH | 9 Aug 2017 | 31 Jul 2018 | Completed | On track |
| Hubtown Solaris P51800001465 | Mumbai Suburban MH | 28 Jul 2017 | 30 Dec 2022 | Completed | On track |
| Hubtown Sunmist A 6th to Above Floor P51800001202 | Mumbai Suburban MH | 27 Jul 2017 | 31 Dec 2019 | Completed | On track |
| Hubtown Premiere Residences - Beverly P51800002671 | Mumbai Suburban MH | 2 Aug 2017 | 31 Jul 2029 | Completed | On track |
| Hubtown Premiere Residences - Commercial P51800003575 | Mumbai Suburban MH | 5 Aug 2017 | 31 Jul 2026 | In progress | On track |
| Hubtown Premiere Residences - Malibu P51800005224 | Mumbai Suburban MH | 11 Aug 2017 | 31 Jul 2029 | In progress | On track |