IITL-NIMBUS THE EXPRESS PARK VIEW
NAME:IITL-NIMBUS THE EXPRESS PARK VIEW
F17/100
Poor track record
Tracking 4 projects — 3 delivered, 1 still active. 3 of 4 (75%) ran late by an average of 8 months.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
1
Completed
3
Delayed
3 (75%)
Late or overdue
Avg delay
8 mo
Worst: 18 mo
On-time rate
33%
Of completed projects
Extension rate
75%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| IITL NIMBUS THE EXPRESS PARK VIEW (TOWER I1, J1, K1) UPRERAPRJ10246 | UP | 14 Aug 2017 | 31 Mar 2019 | Completed | 18 mo delay |
| THE EXPRESS PARK VIEW II- LOW RISE APARTMENTS UPRERAPRJ555694 | Gautam Buddha Nagar UP | 31 Mar 2021 | 23 Jan 2024 | Overdue | 17 mo overdue |
| IITL NIMBUS THE EXPRESS PARK VIEW (TOWER L,L1,M,M1 UPRERAPRJ10096 | UP | 14 Aug 2017 | 31 Dec 2018 | Completed | On track |
| THE PARK STREET UPRERAPRJ180127 | UP | 31 Oct 2019 | 31 Mar 2021 | Completed | 6 mo delay |