Larsen & Toubro Ltd. (Realty Division)
NAME:Larsen & Toubro Ltd. (Realty Division)
B73/100
Good track record
Tracking 4 projects — 4 delivered, 0 still active. 1 of 4 (25%) ran late by an average of 2 months.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
0
Completed
4
Delayed
1 (25%)
Late or overdue
Avg delay
1.5 mo
Worst: 6 mo
On-time rate
75%
Of completed projects
Extension rate
25%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| Emerald Isle - T7 P51800005072 | Mumbai Suburban MH | 9 Aug 2017 | 30 Jun 2018 | Completed | On track |
| Emerald Isle - T8 P51800002230 | Mumbai Suburban MH | 31 Jul 2017 | 31 Dec 2018 | Completed | On track |
| Emerald Isle - T9 P51800007280 | Mumbai Suburban MH | 17 Aug 2017 | 30 Dec 2021 | Completed | On track |
| Emerald Isle - T4, T5, T6 P51800003307 | Mumbai Suburban MH | 5 Aug 2017 | 31 Dec 2017 | Completed | 6 mo delay |