LODHA DEVELOPERS LIMITED
NAME:LODHA DEVELOPERS LIMITED
A80/100
Strong track record
Tracking 33 projects — 30 delivered, 3 still active. 6 of 33 (18%) ran late by an average of 3 months.
Delivery breakdown
How this builder's 33 tracked projects are split by outcome.
Key numbers
Total projects
33
Active
3
Completed
30
Delayed
6 (18%)
Late or overdue
Avg delay
2.6 mo
Worst: 30 mo
On-time rate
87%
Of completed projects
Extension rate
21%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (33)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| Lodha Signet Lower Parel Wing A P51900029416 | Mumbai City MH | 29 May 2021 | 30 May 2025 | Completed | On track |
| Lodha NCP Tower - 1 P51900034170 | Mumbai City MH | 25 Mar 2022 | 31 Dec 2026 | Completed | On track |
| LODHA SPLENDORA - PLATINO - D P51700000659 | Thane MH | 19 Jul 2017 | 30 Sept 2022 | Overdue | 45 mo overdue |
| Lodha NCP Tower - 2 P51900046324 | Mumbai City MH | 22 Jun 2022 | 31 May 2029 | In progress | On track |
| Lodha Signet Lower Parel Wing B P51900046367 | Mumbai City MH | 22 Jun 2022 | 31 Aug 2026 | Completed | On track |
| LODHA AMARA - TOWER 26, 27, 28, 30, 34, 35 P51700001031 | Thane MH | 25 Jul 2017 | 30 Dec 2021 | Completed | On track |
| Upper Thane Ecopolis A - B P51700007192 | Thane MH | 17 Aug 2017 | 30 Sept 2022 | Completed | On track |
| Lodha Fiorenza P51800000195 | Mumbai Suburban MH | 10 Jul 2017 | 31 Jan 2018 | Completed | On track |
| LODHA ETERNIS NATURA A P51800000345 | Mumbai Suburban MH | 15 Jul 2017 | 30 May 2022 | Completed | On track |
| LODHA AMARA - TOWER 32,33 P51700001030 | Thane MH | 25 Jul 2017 | 28 Aug 2022 | Completed | On track |
| NEW CUFFE PARADE - LODHA DIORO AND ELISIUM P51900000314 | Mumbai City MH | 15 Jul 2017 | 30 Jun 2018 | Completed | 12 mo delay |
| CASA UNIVIS - CIELO D P51700001153 | Thane MH | 26 Jul 2017 | 31 Mar 2018 | Completed | On track |
| NCP Commercial Tower - Supremus P51900021485 | Mumbai City MH | 5 Jul 2019 | 30 Mar 2024 | Completed | On track |
| Lodha Lower Parel Project P51900022245 | Mumbai City MH | 5 Sept 2019 | 30 Dec 2024 | Completed | On track |
| LODHA AMARA - TOWER 1 - 5, 7 - 19 P51700001065 | Thane MH | 25 Jul 2017 | 30 Nov 2019 | Completed | On track |
| LODHA ETERNIS SERENA A P51800000294 | Mumbai Suburban MH | 13 Jul 2017 | 31 Dec 2019 | Completed | On track |
| LODHA SPLENDORA - PLATINO - B P51700000258 | Thane MH | 10 Jul 2017 | 31 Mar 2019 | Completed | On track |
| LODHA AMARA - TOWER 29,31 P51700000981 | Thane MH | 25 Jul 2017 | 30 Jul 2022 | Completed | On track |
| NEW CUFFE PARADE - LODHA ENCHANTE P51900000367 | Mumbai City MH | 15 Jul 2017 | 30 Jun 2018 | Completed | 12 mo delay |
| New Cuffe Parade - Lodha Gardenia P51900015715 | Mumbai City MH | 19 Mar 2018 | 30 Mar 2023 | Completed | On track |
| LODHA PARK - TOWN HOUSES P51900016526 | Mumbai City MH | 21 May 2018 | 30 Dec 2021 | Completed | On track |
| NCP Commercial Tower 1 - Floors 24 to 28 P51900017945 | Mumbai City MH | 28 Sept 2018 | 30 Jun 2019 | Completed | On track |
| NCP Commercial Tower 1 - up to 22nd Floor P51900022549 | Mumbai City MH | 1 Oct 2019 | 31 Dec 2019 | Completed | On track |
| LODHA SPLENDORA PLATINO E TO G , VIVANT A TO D P51700000199 | Thane MH | 10 Jul 2017 | 30 Jun 2019 | Completed | On track |
| Upper Thane Greenville A - E, E1, F - I P51700006147 | Thane MH | 14 Aug 2017 | 30 Sept 2022 | Completed | On track |
| Upper Thane Treetops A - C, C1, C2, D - F P51700008449 | Thane MH | 19 Aug 2017 | 30 Sept 2022 | Completed | On track |
| LODHA ETERNIS IDYLLIA B, SERENA B, NATURA B AND C P51800000293 | Mumbai Suburban MH | 13 Jul 2017 | 31 Dec 2018 | Completed | On track |
| NEW CUFFE PARADE - LODHA ESTRELLA P51900000521 | Mumbai City MH | 18 Jul 2017 | 31 Jan 2019 | Completed | On track |
| NEW CUFFE PARADE - LODHA EVOQ 41st Floor P51900000567 | Mumbai City MH | 18 Jul 2017 | 30 Jun 2018 | Completed | 30 mo delay |
| NEW CUFFE PARADE -LODHA ALTIA P51900000629 | Mumbai City MH | 18 Jul 2017 | 30 Mar 2022 | Completed | On track |
| LODHA PARK P51900001339 | Mumbai City MH | 27 Jul 2017 | 31 Dec 2021 | Completed | 24 mo delay |
| Lodha Adrina P51900014937 | Mumbai City MH | 15 Jan 2018 | 31 Jul 2024 | Overdue | 23 mo overdue |
| NCP Commercial Tower 1 - Floor 23rd P51900019176 | Mumbai City MH | 9 Jan 2019 | 30 Sept 2019 | Completed | On track |