MIST DIRECT SALES PRIVATE LIMITED
NAME:MIST DIRECT SALES PRIVATE LIMITED
F0/100
Poor track record
Tracking 2 projects — 0 delivered, 2 still active. 2 of 2 (100%) ran late. Limited history — read the project list before drawing conclusions.
This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.
Delivery breakdown
How this builder's 2 tracked projects are split by outcome.
Key numbers
Total projects
2
Active
2
Completed
0
Delayed
2 (100%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
100%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (2)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| Festival City Phase-II UPRERAPRJ3056 | Gautam Buddha Nagar UP | 2 Aug 2017 | 11 Jul 2024 | Overdue | 17 mo overdue |
| Festival City Phase-III UPRERAPRJ3088 | Gautam Buddha Nagar UP | 2 Aug 2017 | 10 Jan 2025 | Overdue | 11 mo overdue |