PARSVNATH DEVELOPERS LIMITED

NAME:PARSVNATH DEVELOPERS LIMITED

Poor track record

Tracking 6 projects — 6 delivered, 0 still active. 5 of 6 (83%) ran late by an average of 11 months.

Delivery breakdown

How this builder's 6 tracked projects are split by outcome.

1 Delivered on time5 Delivered late

Key numbers

Total projects

6

Active

0

Completed

6

Delayed

5 (83%)

Late or overdue

Avg delay

10.6 mo

Worst: 23.5 mo

On-time rate

17%

Of completed projects

Extension rate

83%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (6)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
PARSVNATH PRIVILEGE PHASE-II
UPRERAPRJ6067
UP
1 Aug 201731 Jul 2019CompletedOn track
PARSVNATH PALACIA PHASE-I
UPRERAPRJ6091
UP
31 Jul 201731 Dec 2019Completed23 mo delay
PARSVNATH PALACIA PHASE-II
UPRERAPRJ6095
UP
31 Jul 201731 Mar 2021Completed16 mo delay
PARSVNATH PRIVILEGE PHASE-III
UPRERAPRJ6076
UP
31 Jul 201731 Jul 2021Completed6 mo delay
PARSVNATH PRIVILEGE PHASE-IV
UPRERAPRJ6081
UP
31 Jul 201731 Dec 2021Completed6 mo delay
PARSVNATH PRIVILEGE PHASE-1
UPRERAPRJ6060
UP
30 Jul 201731 Jan 2019Completed12 mo delay