PARSVNATH DEVELOPERS LIMITED
NAME:PARSVNATH DEVELOPERS LIMITED
F2/100
Poor track record
Tracking 6 projects — 6 delivered, 0 still active. 5 of 6 (83%) ran late by an average of 11 months.
Delivery breakdown
How this builder's 6 tracked projects are split by outcome.
Key numbers
Total projects
6
Active
0
Completed
6
Delayed
5 (83%)
Late or overdue
Avg delay
10.6 mo
Worst: 23.5 mo
On-time rate
17%
Of completed projects
Extension rate
83%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (6)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| PARSVNATH PRIVILEGE PHASE-II UPRERAPRJ6067 | UP | 1 Aug 2017 | 31 Jul 2019 | Completed | On track |
| PARSVNATH PALACIA PHASE-I UPRERAPRJ6091 | UP | 31 Jul 2017 | 31 Dec 2019 | Completed | 23 mo delay |
| PARSVNATH PALACIA PHASE-II UPRERAPRJ6095 | UP | 31 Jul 2017 | 31 Mar 2021 | Completed | 16 mo delay |
| PARSVNATH PRIVILEGE PHASE-III UPRERAPRJ6076 | UP | 31 Jul 2017 | 31 Jul 2021 | Completed | 6 mo delay |
| PARSVNATH PRIVILEGE PHASE-IV UPRERAPRJ6081 | UP | 31 Jul 2017 | 31 Dec 2021 | Completed | 6 mo delay |
| PARSVNATH PRIVILEGE PHASE-1 UPRERAPRJ6060 | UP | 30 Jul 2017 | 31 Jan 2019 | Completed | 12 mo delay |