REGENCY NIRMAN LTD
NAME:REGENCY NIRMAN LTD
D43/100
Weak track record
Tracking 6 projects — 6 delivered, 0 still active. 3 of 6 (50%) ran late by an average of 5 months.
Delivery breakdown
How this builder's 6 tracked projects are split by outcome.
Key numbers
Total projects
6
Active
0
Completed
6
Delayed
3 (50%)
Late or overdue
Avg delay
5 mo
Worst: 18 mo
On-time rate
50%
Of completed projects
Extension rate
50%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (6)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| Regency Antilia Phase - II P51700002911 | Thane MH | 4 Aug 2017 | 31 Dec 2018 | Completed | 6 mo delay |
| Regency Sarvam Phase - 9 P51700007066 | Thane MH | 17 Aug 2017 | 30 Jun 2018 | Completed | On track |
| Regency Antilia Phase - I P51700002735 | Thane MH | 4 Aug 2017 | 31 Dec 2018 | Completed | 6 mo delay |
| Regency Sarvam Phase - 8 P51700002824 | Thane MH | 4 Aug 2017 | 31 Aug 2018 | Completed | On track |
| Regency Sarvam Phase - 10 P51700007704 | Thane MH | 17 Aug 2017 | 31 Dec 2019 | Completed | On track |
| Regency Antilia Phase - III P51700008116 | Thane MH | 18 Aug 2017 | 30 Jun 2019 | Completed | 18 mo delay |