Rite Developers Pvt. Ltd.

RERA delivery track record · complaints · project delays

NAME:RITE DEVELOPERS

Poor track record

Tracking 10 projects — 4 delivered, 6 still active. 8 of 10 (80%) ran late by an average of 6 months.

Delivery breakdown

How this builder's 10 tracked projects are split by outcome.

2 Delivered on time2 Delivered late6 Overdue

Key numbers

Total projects

10

Active

6

Completed

4

Delayed

8 (80%)

Late or overdue

Avg delay

6 mo

Worst: 12 mo

On-time rate

50%

Of completed projects

Extension rate

70%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (10)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800009215
Mumbai Suburban · MH
Mumbai Suburban
MH
22 Aug 201730 Jun 2021Overdue30 mo overdue
P51800009491
Mumbai Suburban · MH
Mumbai Suburban
MH
22 Aug 201731 Dec 2018Overdue51 mo overdue
P51800010335
Mumbai Suburban · MH
Mumbai Suburban
MH
24 Aug 201730 Apr 2022Overdue44 mo overdue
P51800006927
Mumbai Suburban · MH
Mumbai Suburban
MH
16 Aug 201731 Dec 2017Completed12 mo delay
P51800010472
Mumbai Suburban · MH
Mumbai Suburban
MH
28 Aug 201731 Dec 2017CompletedOn track
P51800004974
Mumbai Suburban · MH
Mumbai Suburban
MH
9 Aug 201731 Dec 2017CompletedOn track
P51800006893
Mumbai Suburban · MH
Mumbai Suburban
MH
16 Aug 201731 Dec 2018Overdue54 mo overdue
P51800026851
Mumbai Suburban · MH
Mumbai Suburban
MH
31 Oct 202030 Sept 2022Overdue45 mo overdue
P51800005813
Mumbai Suburban · MH
Mumbai Suburban
MH
14 Aug 201730 Mar 2021Overdue51 mo overdue
P51800006260
Mumbai Suburban · MH
Mumbai Suburban
MH
14 Aug 201731 Dec 2018Completed12 mo delay