← Back to search

Rite Advent

P51800009491

Mumbai Suburban, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 51 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 22 Aug 2017Due 30 Mar 2022

Past deadline by ~51 months.

  1. Registered with RERA

    22 Aug 2017
  2. Original promised completion

    31 Dec 2018

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    30 Mar 2022

    Pushed back ~39 months across 1 extension.

  4. Today — still not completed

    About 51 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

22 Aug 2017

When the project was registered with RERA.

31 Dec 2018

The deadline committed to at registration.

30 Mar 2022

After all approved extensions.

Handover date, when available.

51 mo overdue50.7 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

2

Complaints against the builder

0

Often reported per project on MahaRERA

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Dec 201830 Mar 2022MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 4 projects — 1 delivered, 3 still active. 4 of 4 (100%) ran late by an average of 12 months.

4 projects4 delayed (100%)0% on time

See Rite Developers Pvt. Ltd.'s full track record →

Official records

View this project on the MahaRERA portal

Builder: Rite Developers Pvt. Ltd. (NAME:Rite Developers Pvt. Ltd.)

Data last refreshed 21 Jun 2026.