VAGAD CONSTRUCTIONS

NAME:VAGAD CONSTRUCTIONS

Poor track record

Tracking 2 projects — 2 delivered, 0 still active. 2 of 2 (100%) ran late by an average of 38 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

2 Delivered late

Key numbers

Total projects

2

Active

0

Completed

2

Delayed

2 (100%)

Late or overdue

Avg delay

37.6 mo

Worst: 63.1 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
AKSHAR ELITA
P51700005621
Thane
MH
11 Aug 201731 Dec 2019Completed63 mo delay
AKSHAR EDEANIA
P52000006744
Raigarh
MH
16 Aug 201731 Dec 2018Completed12 mo delay