AKSHAR ELITA

P51700005621

Thane, MaharashtraOthersCompleted

Delivered — but late

This project was completed about 63 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 11 Aug 2017Due 4 Apr 2025

Completed.

  1. Registered with RERA

    11 Aug 2017
  2. Original promised completion

    31 Dec 2019

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    4 Apr 2025

    Pushed back ~63 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

11 Aug 2017

When the project was registered with RERA.

31 Dec 2019

The deadline committed to at registration.

4 Apr 2025

After all approved extensions.

Handover date, when available.

63 mo delay63.1 mo

How late the finished project was.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Dec 20194 Apr 2025MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 2 projects — 2 delivered, 0 still active. 2 of 2 (100%) ran late by an average of 38 months. Limited history — read the project list before drawing conclusions.

2 projects2 delayed (100%)0% on time

See VAGAD CONSTRUCTIONS's full track record →

Official records

View this project on the MahaRERA portal

Builder: VAGAD CONSTRUCTIONS (NAME:VAGAD CONSTRUCTIONS)

Data last refreshed 21 Jun 2026.