YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY

NAME:YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY

Poor track record

Tracking 13 projects — 4 delivered, 9 still active. 9 of 13 (69%) ran late by an average of 13 months.

Delivery breakdown

How this builder's 13 tracked projects are split by outcome.

1 Delivered on time3 Delivered late6 Overdue3 In progress

Key numbers

Total projects

13

Active

9

Completed

4

Delayed

9 (69%)

Late or overdue

Avg delay

13.5 mo

Worst: 18 mo

On-time rate

25%

Of completed projects

Extension rate

46%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (13)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Convenient Shopping Complex, Sector 22D
UPRERAPRJ15338
Gautam Buddha Nagar
UP
28 Feb 201830 Jun 2018Overdue96 mo overdue
GH-06, SEC-22A, YEIDA, PHASE 1 (YAMUNOTRI)
UPRERAPRJ9384
Gautam Buddha Nagar
UP
11 Aug 201731 Mar 2021Overdue57 mo overdue
INDIVIDUAL RESIDENTIAL PLOTS, SEC-17,YEIDA
UPRERAPRJ9318
Gautam Buddha Nagar
UP
11 Aug 201730 Sept 2020Overdue63 mo overdue
RPS 05/2021
UPRERAPRJ146610
Gautam Buddha Nagar
UP
22 Dec 202131 May 2027In progressOn track
RPS01,RRPS01 AND RRPS02 (SECTOR 18 AND 20) ,YEIDA
UPRERAPRJ282078
Gautam Buddha Nagar
UP
15 Oct 20199 Jan 2024Overdue23 mo overdue
RPS-04/2021
UPRERAPRJ552003
Gautam Buddha Nagar
UP
26 Feb 202131 May 2026Overdue1 mo overdue
RPS-06/2022
UPRERAPRJ985835
Gautam Buddha Nagar
UP
2 Sept 202231 Dec 2027In progressOn track
RPS07/2023
UPRERAPRJ563740
Gautam Buddha Nagar
UP
7 Aug 202330 Nov 2028In progressOn track
RRPS -04/2020
UPRERAPRJ205883
Gautam Buddha Nagar
UP
18 Aug 202031 Dec 2025Overdue6 mo overdue
Affordable Housing Sector-22D YEIDA
UPRERAPRJ8647
UP
9 Aug 201728 Dec 2019CompletedOn track
RPS-02, SEC-22D
UPRERAPRJ8756
UP
9 Aug 201710 Sept 2019Completed18 mo delay
Footprints for Commercial Use, Sec-22A
UPRERAPRJ8813
UP
10 Aug 20179 Jul 2019Completed18 mo delay
GH06, Sec-22D, YEIDA
UPRERAPRJ8947
UP
10 Aug 201730 Dec 2019Completed18 mo delay