YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY
NAME:YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY
F18/100
Poor track record
Tracking 13 projects — 4 delivered, 9 still active. 9 of 13 (69%) ran late by an average of 13 months.
Delivery breakdown
How this builder's 13 tracked projects are split by outcome.
Key numbers
Total projects
13
Active
9
Completed
4
Delayed
9 (69%)
Late or overdue
Avg delay
13.5 mo
Worst: 18 mo
On-time rate
25%
Of completed projects
Extension rate
46%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (13)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| Convenient Shopping Complex, Sector 22D UPRERAPRJ15338 | Gautam Buddha Nagar UP | 28 Feb 2018 | 30 Jun 2018 | Overdue | 96 mo overdue |
| GH-06, SEC-22A, YEIDA, PHASE 1 (YAMUNOTRI) UPRERAPRJ9384 | Gautam Buddha Nagar UP | 11 Aug 2017 | 31 Mar 2021 | Overdue | 57 mo overdue |
| INDIVIDUAL RESIDENTIAL PLOTS, SEC-17,YEIDA UPRERAPRJ9318 | Gautam Buddha Nagar UP | 11 Aug 2017 | 30 Sept 2020 | Overdue | 63 mo overdue |
| RPS 05/2021 UPRERAPRJ146610 | Gautam Buddha Nagar UP | 22 Dec 2021 | 31 May 2027 | In progress | On track |
| RPS01,RRPS01 AND RRPS02 (SECTOR 18 AND 20) ,YEIDA UPRERAPRJ282078 | Gautam Buddha Nagar UP | 15 Oct 2019 | 9 Jan 2024 | Overdue | 23 mo overdue |
| RPS-04/2021 UPRERAPRJ552003 | Gautam Buddha Nagar UP | 26 Feb 2021 | 31 May 2026 | Overdue | 1 mo overdue |
| RPS-06/2022 UPRERAPRJ985835 | Gautam Buddha Nagar UP | 2 Sept 2022 | 31 Dec 2027 | In progress | On track |
| RPS07/2023 UPRERAPRJ563740 | Gautam Buddha Nagar UP | 7 Aug 2023 | 30 Nov 2028 | In progress | On track |
| RRPS -04/2020 UPRERAPRJ205883 | Gautam Buddha Nagar UP | 18 Aug 2020 | 31 Dec 2025 | Overdue | 6 mo overdue |
| Affordable Housing Sector-22D YEIDA UPRERAPRJ8647 | UP | 9 Aug 2017 | 28 Dec 2019 | Completed | On track |
| RPS-02, SEC-22D UPRERAPRJ8756 | UP | 9 Aug 2017 | 10 Sept 2019 | Completed | 18 mo delay |
| Footprints for Commercial Use, Sec-22A UPRERAPRJ8813 | UP | 10 Aug 2017 | 9 Jul 2019 | Completed | 18 mo delay |
| GH06, Sec-22D, YEIDA UPRERAPRJ8947 | UP | 10 Aug 2017 | 30 Dec 2019 | Completed | 18 mo delay |