Footprints for Commercial Use, Sec-22A

UPRERAPRJ8813

Uttar PradeshCompleted

Delivered — but late

This project was completed about 18 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 10 Aug 2017Due 7 Jan 2021

Completed.

  1. Registered with RERA

    10 Aug 2017
  2. Original promised completion

    9 Jul 2019

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    7 Jan 2021

    Pushed back ~18 months across 2 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

10 Aug 2017

When the project was registered with RERA.

9 Jul 2019

The deadline committed to at registration.

7 Jan 2021

After all approved extensions.

Handover date, when available.

18 mo delay18 mo

How late the finished project was.

2

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
9 Jul 20198 Jul 2020
8 Jul 20207 Jan 202107-01-2021 (Six months extension in view of force majeure caused by covid-19 pandemic)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 13 projects — 4 delivered, 9 still active. 9 of 13 (69%) ran late by an average of 13 months.

13 projects9 delayed (69%)25% on time

See YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY's full track record →

Official records

View this project on the UP RERA portal

Builder: YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY (NAME:YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY)

Data last refreshed 21 Jun 2026.