Enigma Towers A and B
P51800002656
Delivered — but late
This project was completed about 19 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
2 Aug 2017Original promised completion
30 Dec 2022The deadline the builder committed to at registration.
Revised deadline after extensions
1 Aug 2024Pushed back ~19 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
2 Aug 2017
When the project was registered with RERA.
30 Dec 2022
The deadline committed to at registration.
1 Aug 2024
After all approved extensions.
—
Handover date, when available.
19 mo delay19.1 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
15
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Dec 2022 | 1 Aug 2024 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 3 projects — 2 delivered, 1 still active. 2 of 3 (67%) ran late by an average of 10 months.
Official records
Builder: Oberoi Constructions Limited (NAME:Oberoi Constructions Limited)
Data last refreshed 21 Jun 2026.