Oberoi Constructions Limited
RERA delivery track record · complaints · project delays
NAME:OBEROI CONSTRUCTIONS
D48/100
Weak track record
Tracking 4 projects — 3 delivered, 1 still active. 2 of 4 (50%) ran late by an average of 6 months.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
1
Completed
3
Delayed
2 (50%)
Late or overdue
Avg delay
6.4 mo
Worst: 19.1 mo
On-time rate
67%
Of completed projects
Extension rate
50%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800004199 Mumbai Suburban · MH | Mumbai Suburban MH | 8 Aug 2017 | 30 Jun 2018 | Completed | On track |
P51800002656 Mumbai Suburban · MH | Mumbai Suburban MH | 2 Aug 2017 | 30 Dec 2022 | Completed | 19 mo delay |
P51800006141 Mumbai Suburban · MH | Mumbai Suburban MH | 14 Aug 2017 | 30 Dec 2022 | Overdue | 1 mo overdue |
P51800017154 Mumbai Suburban · MH | Mumbai Suburban MH | 17 Jul 2018 | 30 Jun 2023 | Completed | On track |